Opinion / WhatsApp Updates
'Zesa failing to connect clinic to power grid'- WhatsApp update
22 May 2014 at 18:01hrs | Views
Please note that Bulawayo24 does not edit WhatsApp updates. We publish them as sent by our readers and we do not disclose the sender's telephone number.
5:18pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: Zenka Clinic electrification. Zesa Kwekwe still to connect Zenka to the power grid. The promised date of 5th of May has come and gone. Zenka clinic deserves and needs to be connected to the power grid in order to offer excellent health services in rural Nkai South. Please exert pressure on Zesa Kwekwe to connect Zenka clinic.
5:21pm, 22 May - Bulawayo24 News: What is Zesa saying about this so far, do you know?
5:23pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: They had promised to connect on the 5th of May, but they have just gone quiet. Rem we aren't allowed to take matters to the media.
5:25pm, 22 May - Bulawayo24 News: Are u part of the Clinic staff?
5:28pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: No, The wiring was inspected and passed. What's left is the connection to the grid. The power grid actually runs through the clinic yard! Zenka clinic relies on gas fridge for vaccines and solar for lighting
5:30pm, 22 May - Bulawayo24 News: Is it a new Clinic?
5:31pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: Old clinic.
5:32pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: General dealer shops, only a few meters away have electricity! Why not a clinic which offers essential health services?
5:38pm, 22 May - Bulawayo24 News: Have you ever tried to get comments from both the Zesa and the clinic about the delay. Maybe there is a genuine reason
5:43pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: Tried but staff there simply say it's now a "cold case" and are afraid to seek clarification directly because of protocol hence I came to you.
7:54pm, 22 May - Bulawayo24 News: Thank you for the update
5:18pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: Zenka Clinic electrification. Zesa Kwekwe still to connect Zenka to the power grid. The promised date of 5th of May has come and gone. Zenka clinic deserves and needs to be connected to the power grid in order to offer excellent health services in rural Nkai South. Please exert pressure on Zesa Kwekwe to connect Zenka clinic.
5:21pm, 22 May - Bulawayo24 News: What is Zesa saying about this so far, do you know?
5:23pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: They had promised to connect on the 5th of May, but they have just gone quiet. Rem we aren't allowed to take matters to the media.
5:25pm, 22 May - Bulawayo24 News: Are u part of the Clinic staff?
5:28pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: No, The wiring was inspected and passed. What's left is the connection to the grid. The power grid actually runs through the clinic yard! Zenka clinic relies on gas fridge for vaccines and solar for lighting
5:31pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: Old clinic.
5:32pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: General dealer shops, only a few meters away have electricity! Why not a clinic which offers essential health services?
5:38pm, 22 May - Bulawayo24 News: Have you ever tried to get comments from both the Zesa and the clinic about the delay. Maybe there is a genuine reason
5:43pm, 22 May - +27 79 ▩▩▩ ▩▩▩▩: Tried but staff there simply say it's now a "cold case" and are afraid to seek clarification directly because of protocol hence I came to you.
7:54pm, 22 May - Bulawayo24 News: Thank you for the update
Source - Byo24News via WhatsApp
All articles and letters published on Bulawayo24 have been independently written by members of Bulawayo24's community. The views of users published on Bulawayo24 are therefore their own and do not necessarily represent the views of Bulawayo24. Bulawayo24 editors also reserve the right to edit or delete any and all comments received.